Installation and Acceptance · Downloadable

What Does Pneumatic Industrial Manipulator Commissioning Include?

Site commissioning covers installation review, pneumatic checks, unloaded testing, load balancing, tooling tests and safety-function verification. Complete a demonstration of the full handling sequence, operator training and records before handing over the equipment for use.

AUREK-RC-AR-007VersionV1.0Updated2026-09-07Read about 9 minutes

Installation and Acceptance
Illustrative image of the topic; it does not show specific equipment or a customer site
← Back to resource catalog
Key points of this article
  • Site commissioning checks installation condition and verifies that the equipment, tooling and safety functions suit the actual workpiece and workstation.
  • Commissioning sequence: installation checks → air connection → unloaded tests → load balancing → tooling/vacuum tests → protective-function tests.
  • Adjustment of load balancing, pneumatic circuits, balancing valves, protective devices and load-bearing structures is the responsibility of the manufacturer or qualified personnel. Do not modify them independently.
  • Use the parameters specified on the equipment nameplate and in the technical proposal, and record settings, test results and training in the site documentation.

Installation location, air-supply condition, working radius, workpiece weight, tooling orientation, operator position and the surrounding layout all affect operation. Site commissioning is still required after factory inspection, covering the actual pickup and placement sequence under site conditions.

01Site commissioning scope

Commissioning should check the mechanical structure, pneumatic system, load balancing, tooling motion, vacuum gripping and safety functions. For equipment with custom tooling, suction cups or a turning mechanism, verify gripping, lifting, movement and placement throughout the actual working envelope, and check the protective functions fitted.

02Preparation for commissioning

Before commissioning, check that the foundation, column, arms, slewing structure, rails or suspension structure are secure. Clear the work area and exclude uninvolved personnel. For pneumatic equipment, also check interfaces, supply condition, air cleanliness, connections and filter-regulator configuration. Prepare the relevant workpiece, tooling, layout dimensions, technical proposal, packing documentation and acceptance records.

03Commissioning procedure

Installation checks

Verify correct installation of the base, column, connection flanges, arm structure, rotary components, rails, and suspended structures; confirm fasteners are secured, travel-limit structures are complete, and the equipment does not interfere with nearby machine tools, conveyors, racks, guards, or personnel aisles. For column-mounted equipment, focus on the foundation, levelness, column verticality, and operating-radius envelope. For overhead-mounted or rail-mounted equipment, focus on the overhead load-bearing structure, suspension points, rail straightness, and travel range.

Air connection and pneumatic checks

The manufacturer or qualified personnel should connect the air supply. Check hoses, fittings, valves, filter-regulators, handles, cylinders and associated circuits for correct connection, leaks, kinks, loose fittings and abnormal responses. Do not independently modify circuits, balancing valves, control valves or safety devices.

Unloaded motion tests

Without a workpiece, test lifting, lowering, slewing, extension/retraction, travel, limits and return. Check for binding, unusual noise, uneven rotation, drift or incorrect speed. Resolve installation, pressure, connection or interference faults before loaded tests.

Load balancing

The manufacturer or qualified personnel should adjust the balance according to workpiece weight, tooling weight and working radius. Test at different heights, extensions and angles, observing stability during lifting, holding position, movement and placement. Record the actual settings within the equipment's permitted range.

Custom-tooling tests

First test jaw opening and closing, locating contact, cylinders, locking mechanisms, handle buttons, release logic and drop-prevention measures without a workpiece. Then test with a workpiece under the low-risk trial-gripping requirements. If gripping is unstable or there is positioning error, interference or abnormal release, have qualified personnel correct the issue and retest.

Vacuum-gripping tests

Use the actual workpiece to check suction-cup contact, vacuum build-up and release, gripping position and lifting condition. Consider material, roughness, flatness, porosity, oil and dust. Verify vacuum pressure, holding capacity and safety margin against the equipment's technical requirements, and retain the test records.

Safety protection, rotation and braking tests

Test travel limits, drop prevention, air-loss protection, protection against incorrect operation, emergency stops and release logic as fitted. For slewing equipment, verify range, damping, braking and positioning. Keep the swept area clear of pedestrian aisles, forklift routes and other equipment motion. Reassess safety zones if the layout changes.

04Commissioning checklist

04 Commissioning checklist — data table
StepTaskKey checksPrecautions
1Installation checksBase, column, arm, rails, fasteners and travel limitsComplete installation checks before testing motion
2Air connectionSupply pressure, fittings, valves and filter-regulatorUse nameplate and technical-design parameters; record site settings
3Pneumatic line inspectionLeaks, loose fittings and kinked hosesDo not modify circuits or valves independently
4Unloaded motion testsSmooth lifting, lowering, slewing, extension/retraction and travelStop and investigate binding or abnormal response
5Load balancingSettings matched to workpiece and tooling weight; stable holding and movementDo not adjust the balance valve and load-bearing structure without permission
6Custom-tooling testsJaws, location, locking, release and drop preventionTest without a workpiece first, then with one
7Vacuum-gripping testsCup contact, pickup, lifting and releaseWorkpiece surface conditions will affect the vacuum-gripping performance
8Protective-function testsLimits, drop prevention, air-loss protection and prevention of incorrect operationDo not remove or bypass safety devices without authorization
9Slewing and braking testsRotation range, braking effect, positioning statusAvoid interference with personnel passages and peripheral equipment
10Training and handoverOperating methods, inspection requirements and abnormal-condition proceduresComplete handover records after training

05Operator training and handover records

After commissioning, the manufacturer or qualified personnel should provide equipment-specific training on the structure, handles, pickup and placement, balanced operation, tooling and suction cups, daily checks and abnormal shutdown. Training must identify daily inspection points and the pneumatic circuits, balancing valves, safety devices, load-bearing structures and tooling connections that must not be adjusted without authorization.

Demonstrate pickup, lifting, movement, placement and reset using the actual workpiece. Record the equipment number, workpiece information, commissioning condition, trainees and site results. If workpiece weight, dimensions, material or the handling path changes, contact AUREK to reassess suitability.

Need installation and commissioning support? Share the equipment model, workpiece information and site conditions. AUREK can arrange installation, commissioning and handover training by qualified personnel.
View the daily inspection checklist

Common questions

Why is commissioning required after installation?

Installation establishes the equipment position. Verify mounting, air connection, unloaded movement, balancing, tooling and safety functions against the actual site before putting it into service.

May users adjust load balancing themselves?

Balancing affects load support, pneumatics and operating safety. The manufacturer or qualified personnel should make adjustments. Users must not independently modify balancing valves, circuits or load-bearing structures.

Does holding one sample prove that vacuum tooling is ready for production?

Holding a sample only demonstrates that vacuum could be established at that particular contact. Before use, complete tests for the actual surface, handling path, lifting height, release position and safety configuration, and record the vacuum parameters and operating results.

What should custom-tooling commissioning cover?

Verify stable gripping, accurate positioning, smooth release, clearance throughout the movement, and the required protection against dropped loads and incorrect operation.

Can the same equipment handle a different workpiece after commissioning?

Reassessment is required if weight, dimensions, material, center of gravity or movements change. These can affect balancing, tooling compatibility and protective functions. Contact AUREK before using the new workpiece.

Related resources

Open resource center
Maintenance and Troubleshooting

AUREK-RC-MT-001Downloadable

Daily Inspection Checklist for Pneumatic Industrial Manipulators

Pre-start and periodic inspection items with records of abnormalities, corrective actions and responsible-person signatures. The form can be printed for team checks, shift handover and maintenance filing.

Maintenance and TroubleshootingVersion V1.0Updated 2026-09-07

Need documents or a proposal for your site?

For documents, drawings or a selection proposal specific to your workpiece and site conditions, share the workpiece and workstation details and an engineer will contact you directly.

AUREK WeChat QR code
WeChatScan to add an engineer and send drawings, photographs or site video, or email sales@aurek.cn.