Installation and Acceptance · Downloadable

Pneumatic Industrial Manipulator Factory Acceptance Test Record

Record pre-shipment inspections, measured evidence, deviation handling and authorized signatures. Inspection items and acceptance criteria are taken from the approved order, technical agreement, drawings and inspection plan.

AUREK-QA-FAT-001VersionV1.0Updated2026-09-07

Installation and Acceptance
Illustrative image of the topic; it does not show specific equipment or a customer site
← Back to resource catalog
Key points
  • Determine whether each inspection item applies, then record Pass, Fail or Rectification Required together with supporting evidence.
  • Enter the load, stroke, pressure, cycle-time and cycle-count requirements from controlled project documents. This general template does not preset those values.
  • Spreadsheet formulas check record completeness only. Authorized personnel review outstanding items and risks before signing the shipment release.

01Purpose

Use this form to inspect and document the pneumatic industrial manipulator and its tooling before shipment. It covers identification, manufacturing records, assembly, functional tests, load range, tooling safety, packaging release and outstanding issues. Identify any factory acceptance items that require further verification on site.

02Roles and responsibilities

  • Manufacturing, assembly, quality, project management and shipment-release personnel.
  • Customer, end-user or third-party representatives witnessing FAT.
  • Project personnel responsible for tooling, safety logic, equipment documents, packaging, transport and closure of outstanding issues.

03How to use

StepRequirements
1. Establish the approved basisRecord the project, equipment, serial number, date and acceptance documents. Reference approved documents for capacities and limits.
2. Check applicabilityMark each item Applicable or Not Applicable. Give a reason for every exclusion; an exclusion must not conceal an incomplete required inspection.
3. Perform inspectionsCover document identification, appearance and assembly, basic functions, load range, tooling, safety, performance and packaging.
4. Record evidenceEnter measurements, observations, photographs, records or document references. The inspector must date the entry.
5. Close deviationsList failed items and required rectifications, with actions, responsible persons, deadlines and closure evidence.
6. Authorize releaseRecord the shipment decision, any conditions, SAT follow-up items, and the approving person or document reference.

04Acceptance scope

CategoryTypical checks
Identification and assemblyNameplate, model, manufacturing records, supplied documents, structural parts, fasteners, air lines, cables and surface protection.
Functions and loadUnloaded full-stroke travel, joint brakes, operating logic, agreed load, reach and representative cycles.
Tooling and safetyWorkpiece fit, retention and release, unintended-release prevention, pressure-loss states, emergency stops, limits and collision prevention.
Release and transportSupplied accessories, spares and tools, transport restraints, protective packaging, deviation approval and SAT follow-up requirements.

05Recording and release requirements

Safety and release requirements:This form does not prescribe or infer fixed loads, strokes, pressures, cycle times or cycle counts. Qualified personnel must conduct safety and load tests under controlled risk conditions, using actual workpieces or verified equivalent loads and staying strictly within the agreed operating conditions. Overloading is prohibited. Formula outputs indicate record completeness only; they do not replace authorized signatures, risk assessment or written deviation approval.
Recommended records:File the completed FAT form, original test records, photographs, deviation approvals and closure evidence together under the equipment serial number.
Read the delivery acceptance guide

Related resources

Open resource center
Installation and Acceptance

AUREK-RC-IN-001Downloadable

Pre-installation Site Confirmation Checklist

Check installation information for the workpiece, motions, foundation, utilities and safety conditions, with supporting site photographs and responsible-person records for design assessment and installation preparation.

Installation and AcceptanceVersion V1.0Updated 2026-09-07

Installation and Acceptance

AUREK-RC-SV-001Downloadable

Site Survey and Photography Checklist

Collect workpiece, handling-path, foundation, clearance and utility data with supporting photographs and file references, making measurement datums, document references and missing information easy to check.

Installation and AcceptanceVersion V1.0Updated 2026-09-07

Need documents or a proposal for your site?

For documents, drawings or a selection proposal specific to your workpiece and site conditions, share the workpiece and workstation details and an engineer will contact you directly.

AUREK WeChat QR code
WeChatScan to add an engineer and send drawings, photographs or site video, or email sales@aurek.cn.