Installation and Acceptance · Downloadable

Pneumatic Industrial Manipulator Site Acceptance Test Record

Record site acceptance after installation and commissioning, covering mounting, operating range, utilities, load, tooling, safety functions, trial handling and training.

AUREK-QA-SAT-001VersionV1.0Updated2026-09-07

Installation and Acceptance
Illustrative image of the topic; it does not show specific equipment or a customer site
← Back to resource catalog
Key points
  • SAT verifies the actual installation and complete operating sequence. FAT records cannot directly replace site acceptance findings.
  • Support each applicable inspection item with a measurement, observation, photograph or document reference. Track rectification items separately through closure.
  • Spreadsheet formulas reflect record completion only. Equipment acceptance, conditions and restrictions require authorized signatures.

01Purpose

Use this form to inspect and record the pneumatic industrial manipulator and tooling after installation and commissioning. It covers transport condition, mounting, reach, site utilities, unloaded and loaded operation, tooling safety and the complete handling sequence, along with operating feel, supplied documents and training. Record the disposition of outstanding issues for the receiving party's review.

02Roles and responsibilities

  • Customer equipment, process, production, maintenance and safety personnel.
  • AUREK project personnel responsible for site installation, commissioning, training and delivery.
  • Authorized representatives witnessing acceptance, reviewing outstanding issues or signing final receipt.

03How to use

StepRequirements
1. Record the acceptance basisRecord the equipment, project, installation location, SAT date and approved technical and acceptance documents.
2. Inspect installationCheck transport damage, structural connections, foundation or suspension mounting, bolt retention, vertical and horizontal alignment, and clearances.
3. Verify functionVerify each pick-and-place point, travel coverage, air supply, leakage, unloaded full-stroke operation and the agreed load.
4. Verify tooling safetyUse actual workpieces or verified equivalent loads to check fit, retention, release, pressure-loss response and personnel protection.
5. Run representative sequencesComplete the entire pickup-to-placement sequence. Record turnover and positioning, actual cycle time, operating feel, noise, vibration and leakage.
6. Complete handoverCheck documents and training, list outstanding issues, and record acceptance conditions, restrictions and closure requirements before signing.

04Acceptance scope

CategoryTypical checks
Installation and operating rangeLayout, mounting, clearances, pick-and-place points, lifting and horizontal coverage, rotation and turnover directions, and interference.
Utilities and operationAir quality and interfaces, sealing and leakage, filtration and drainage, unloaded full-stroke travel, the agreed load and cycle stability.
Tooling and safetyWorkpiece fit, retention and release, unintended-release prevention, pressure loss, emergency stops, limits, buffers and warning labels.
Handover and personnelActual cycle time, operating experience, supplied documents, operator and maintenance training, abnormal-condition response and responsibility for outstanding issues.

05Acceptance records and handover

Safety and acceptance requirements:Equipment capacities and acceptance limits must reference approved documents; do not enter unverified fixed values in this general form. Load tests must use actual workpieces or mutually accepted equivalent loads and remain within the agreed conditions. Overloading is prohibited. Qualified personnel must conduct safety tests under site risk controls. Formula results do not replace authorized written assessment of outstanding issues, risks, conditions or operating restrictions.
After acceptance:Retain temporary measures or operating restrictions for open items until the completion date, closure evidence and verifying person have all been recorded.
Read the delivery acceptance guide

Related resources

Open resource center
Installation and Acceptance

AUREK-RC-IN-001Downloadable

Pre-installation Site Confirmation Checklist

Check installation information for the workpiece, motions, foundation, utilities and safety conditions, with supporting site photographs and responsible-person records for design assessment and installation preparation.

Installation and AcceptanceVersion V1.0Updated 2026-09-07

Installation and Acceptance

AUREK-RC-SV-001Downloadable

Site Survey and Photography Checklist

Collect workpiece, handling-path, foundation, clearance and utility data with supporting photographs and file references, making measurement datums, document references and missing information easy to check.

Installation and AcceptanceVersion V1.0Updated 2026-09-07

Need documents or a proposal for your site?

For documents, drawings or a selection proposal specific to your workpiece and site conditions, share the workpiece and workstation details and an engineer will contact you directly.

AUREK WeChat QR code
WeChatScan to add an engineer and send drawings, photographs or site video, or email sales@aurek.cn.